July → September 2024
Consultation with Community Sporting Groups
September 2024
Concept Design & Feasibility Investigation
01 February 2025
Secured State Government Funding
September 2025
Detailed Design Completed
October 2025
Tender Advertisement
29 January 2025
Tender Award at January OCM
01 February 2026
Contract Signing
February → August 2026
Construction Period
August 2026
Official Opening